What we plan to build, and what it means for you
StratGrid is planning a digital infrastructure campus with its own natural gas power plant east of Calgary. Here is what we know, what we're working on, what we don't know yet, and how to reach us.
The Project in three numbers
Digital infrastructure means buildings full of computers that store and process information. Ours would produce its own electricity on site, so it would not draw power from Alberta's grid. There will be no impact on local grid capacity or to your electricity bill.
These are StratGrid's own estimates as of November 2026. They may change as the Project advances and regulators review the plans.
- Power plant, net power240megawatts
The plant would run on natural gas and power the campus. We will use low noise, low emissions, high efficiency generators.
- Land146hectares
That is 360 acres, or a little more than a half-section. The land is privately owned, not Crown land, and is located in a designated industrial node.
- Earliest start – Q42028
This is our target for first power. It depends on approvals we are seeking or presently developing, which we anticipate receiving throughout 2027.

Who we are
We are an Alberta-based private company founded in 2025. Nearly all of our directors and executives call Alberta home. We grew up here, we work here, we've raised our families here. In every aspect of the Project's development we will show our love for the land and respect for the people who live here.
Meet the teamWhat it could bring, and what it would change
We know a project like this will have impacts. We are focused on making the most of the positives and keeping the negatives as small as we can. Some quantitative measures are not yet available and will be shared here as they become available.
Impacts we are planning for
We are protecting the electricity grid by leaving it undisturbed. We also know the concerns about water, air, noise and traffic that projects like this face, and our goal is to use the best solution available.
Benefits we can create
Jobs, local business support, community involvement and investment, tax revenue at all levels of government, better infrastructure, and royalties to the Province.
Benefits still to come
Some we can't measure yet. Access to this much computing could open doors in education, research and development, and lead to new ideas grown here at home.
What we plan to do about it
The design is not finished, so these are plans, not promises. Each page explains what we can commit to today and what still depends on engineering refinement and review.
Water
Cooling water will be run in a sealed closed loop system and will be continuously recycled and reused over and over, instead of being used once.
A sealed loop
Computers warm the water, coolers cool it again, and it goes back around.
Small top-ups only
Small volumes of make up water are required periodically. Water will be drawn from an existing non-potable raw water industrial pipeline.
Office utilities
Aside from minimal top-ups, office utilities are the only planned daily use and discharge sources.
Sound
A power plant and cooling equipment make noise. The plan is to cut it down in steps between the equipment and the nearest home.
Quieter equipment
We plan to choose machines that make less noise to start with.
Sound barriers
Walls and enclosures will go around the loudest parts.
Distance
The power plant will sit back from the property line.
Berms and landscaping
We will use earth berms and dense landscaping to absorb ambient noise.
Views and light at night
Buildings are planned to be low and set back from the road, with trees in front and lights that point down.
These sketches show the idea only. They are not drawings of the site.
The wheels are turning
The Project needs approval from applicable local, provincial and environmental regulatory bodies before anything is built. These are our proposed target dates.
- May 2026, complete
Land secured
We secured the land and began early talks with regulators.
- We are here2026 to 2027
Design and applications
Engineering continues and we file regulatory applications. This is where your input shapes the plans.
- Late 2027, target
Decisions on approvals
Regulators decide whether the Project can go ahead, and on what conditions.
- 2027 to 2028, target
Construction
Building and testing. This is the busiest time for trucks and crews.
- Q4 2028, target
First power
The power plant starts up and the first building begins to operate.
Announcements
See all updatesA new place for project information
This site is where we will provide news about the project and corporate updates. If a number changes, it changes here first.
Land secured, and early talks with regulators begin
We secured about 146 hectares (360 acres) of private land east of Calgary and started early conversations with Alberta's regulators.
StratGrid starts up in Calgary
StratGrid Inc. was founded as an Alberta company to plan the Project.
Talk to a person
Call or write with a question, a concern or something we got wrong.